Project Images
Orlando Health Main Campus CEP Cx
Project Summary
Orlando Health chose Hanson to provide commissioning for a new chiller and generator addition, as well as retro-commissioning for its West Central Energy Plant (CEP) in Orlando, Florida.
Hanson’s scope of services encompassed the commissioning of systems and subsystems, including a 2,800-ton, water-cooled centrifugal chiller; an 8,400-gpm, field-erected cooling tower; a chilled water pump; a condenser water pump; controls associated with the chilled and condensed water system; and a 2,250-kilowatt diesel fuel generator and associated 25,000-gallon fuel tank.
Hanson also provided retro-commissioning for the west CEP that included a chiller, a primary chilled water pump, three cooling tower and condenser water pumps, the controls system for the CEP and two generators. Hanson conducted the work during the planning and investigative phases and provided an implementation plan.