Flights have begun at Orlando International Airport’s new Terminal C.
A soft opening was held Sept. 20, with an Aer Lingus flight from Manchester, England, the first to arrive. The 15-gate terminal is the first phase of the airport’s new South Airport Terminal, which connects to the Automated People Mover Complex and Intermodal Terminal Facility that were previously completed. Together, the three facilities comprise a nearly $3 billion addition to the airport.
Hanson provided commissioning during construction of the complex, which has about 1.8 million square feet of conditioned space.